Office copier installation planner
Start with the first day your office needs a working copier. Work back through staff testing, delivery and order approval, and leave time to retest if something fails.
Set your installation dates
The fields start with an example. Enter calendar days, including weekends and closures. Ask the dealer when its lead time starts and when the copier will be installed, with the quoted options in place.
Example milestone dates
- Start internal approval
- November 2, 2027
- Release the order
- November 9, 2027
- Have the copier installed
- December 7, 2027
- Finish the first round of tests
- December 10, 2027
- Have the copier in service
- December 17, 2027
Resolve these items before the order goes out
- Reserve the hardware and the crew. Ask whether the exact copier, feeder, trays and finisher are available together. Get an installation window in writing, including who will handle inside placement, stairs, access and removal.
- Book IT and facilities in parallel. Assign the print queue, authentication and scan destinations to a named person. Have facilities check the route to the room, power and network access. Put those checks on the calendar before the delivery appointment.
- Keep a working fallback. Agree when the old machine can be disconnected and what staff will use if the new one fails a test. If you plan to keep both temporarily, ask how both service agreements bill and whether you have the space and network connections.
For examples of purchasing approval and IT responsibilities, see the published procedures from Illinois State University Purchasing and the University of Idaho Office of Information Technology.
Check delivery, setup and removal costs · Check a separate lease notice or pickup deadline
Test the jobs staff need on day one
Have a regular staff user print from their usual application, copy a job that needs the quoted paper size or finishing, and scan a two-sided sample to a real destination. Open the delivered file as the intended recipient. Record what failed, who owns the fix and when to retest.
If scans go through a capture workflow, run a second sample with a missing field or an out-of-order page and confirm where it goes for review. If you use Ademero’s Paige, ask the installer to demonstrate the actual copier panel, the capture job and the configured destination on the quoted setup.
Before sign-off, ask what your agreement treats as acceptance, when billing starts and how to record unresolved items. Save the starting meters with the acceptance record.
Get the schedule and costs in writing
Ask for the exact model and accessories, the installed price, the proposed dates and who will set up your print and scan jobs.
Request an itemized installation quote